Article Writing Homework Help

Develop the Work Breakdown Structure (WBS) outline and Gantt chart using Microsoft® Project 2016 and the information provided in the textbook. Save your file. Use this file and the information provide

Develop the Work Breakdown Structure (WBS) outline and Gantt chart using Microsoft® Project 2016 and the information provided in the textbook. Save your file.

Get Your Custom Essay Written From Scratch
We have worked on a similar problem. If you need help click order now button and submit your assignment instructions.
Just from $13/Page
Order Now

Use this file and the information provided below to create a project schedule: 

  • The following holidays are observed: January 1, Martin Luther King Day (third Monday in January), Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (fourth Thursday in November), December 25 and 26.
  • If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday then Monday will be given off.
  • The project team works eight-hour days, Monday through Friday.
  • The project will begin on January 3, 2020.

Hints: Change the timescale to months and weeks. The estimated duration of the project is 135 days.